Multiple Choice
The final step in the creation of a Work Breakdown Structure is to
A) Code the WBS for tracking
B) Assign the cost account to a manager
C) Assign the work package to a manager
D) Develop the responsibility matrix
E) All of these are included in the final step
Correct Answer:

Verified
Correct Answer:
Verified