Multiple Choice
Kim is reviewing a proposed project.The scope of the project is narrow with a lot of in-depth expertise required and it will take a short period of time to complete.The best choice for organizing the project is ________ organization.
A) Functional
B) Balanced matrix
C) Weak matrix
D) Strong matrix
E) Project