Multiple Choice
What is the net present value of a project with a cost of $100 000 that generates cash flows of $40 000 over the next three years,and the required rate of return is 15%?
A) $8670
B) -$8670
C) $7890
D) -$5210
Correct Answer:

Verified
Correct Answer:
Verified