Multiple Choice
Noah Construction Company is building a large complex for a contract price of $5,000,000. This is a three-year project estimated to cost $4,000,000 and the following information is available:
-Using the percentage-of-completion method of revenue recognition,how much income is recognized in Year 2?
A) $250,000
B) $375,000
C) $625,000
D) $3,125,000
Correct Answer:

Verified
Correct Answer:
Verified