Multiple Choice
Noah Construction Company is building a large complex for a contract price of $5,000,000. This is a three-year project estimated to cost $4,000,000 and the following information is available:
-Which one of the following entries would be made in Year 2 to record the customer billing using the percentage-of-completion method of revenue recognition?
A) DR Accounts receivable
CR Cash
B) DR Accounts receivable
CR Billings on construction in progress
C) DR Accounts receivable
CR Income on long-term construction contract
D) DR Accounts receivable
CR Billings on construction in progress
Correct Answer:

Verified
Correct Answer:
Verified
Q81: In an effort to "clean up" company
Q82: Peachpit Software Developers shipped its accounting
Q83: The SEC permits Internet resellers (i.e.,those that
Q84: Noah Construction Company is building a
Q85: "Capacity swaps" have been used by telecommunications
Q87: Under the percentage-of-completion method,the profit to be
Q88: The most important criteria related to revenue
Q89: Unlike U.S.GAAP,IFRS calls for revenue to be
Q90: SAB 104,"Revenue Recognition," was not meant to
Q91: When the risk of non-collection of installment