Multiple Choice
Noah Construction Company is building a large complex for a contract price of $5,000,000. This is a three-year project estimated to cost $4,000,000 and the following information is available:
-Which one of the following entries would be made in Year 3 to record the completion and acceptance of the project using the completed-contract method of revenue recognition?
A) DR Inventory: Construction in progress
CR Billings on construction in progress
B) DR Billings on construction in progress
CR Inventory: Construction in progress
CR Income on long-term construction contract
C) DR Inventory: Construction in progress
DR Income on long-term construction contract
CR Billings on construction in progress
D) DR Billings on construction in progress
CR Inventory: Construction in progress
Correct Answer:

Verified
Correct Answer:
Verified
Q44: The SEC specifies four criteria for revenue
Q45: When the outcome of a transaction for
Q46: Ford Appliance Center records revenue on
Q47: Deferred gross profit on installment sales is
Q48: Under IFRS,when the cost recovery method is
Q50: Initial franchise fee revenue should be recognized
Q51: In the context of revenue recognition,an "arrangement"
Q52: Generally accepted accounting principles leave ample room
Q53: Revenue is recognized at the earliest moment
Q54: Revenue is recognized at the earliest moment