Multiple Choice
Which of the following includes a common reason why change occurs?
A) A misunderstanding of the initial scope
B) Shifts in planned technology that force unexpected and significant changes to the business
C) An omission in defining initial scope
D) All the answers are correct
Correct Answer:

Verified
Correct Answer:
Verified