Tina,an Experienced Pool Contractor,and Bruce Agree on a Price for Tina

Question 24

Multiple Choice

Tina,an experienced pool contractor,and Bruce agree on a price for Tina to build a pool in Bruce's backyard.While the area is not known for rocks,unfortunately Tina unexpectedly encounters a significant problem with solid rock in the backyard when she starts to dig.She tells Bruce that unless she receives an extra $5,000,she cannot complete the job.Bruce agrees thinking to himself that he has a way out.When Tina finishes the pool,Bruce refuses to pay the additional $5,000.Which of the following is the most likely result of their dispute?


A) Bruce will be required to pay because a typical, unilateral contract is involved, and he got the benefit of his bargain.
B) Bruce will be required to pay because a typical, bilateral contract is involved, and he got the benefit of his bargain.
C) Bruce will be required to pay because unforeseen circumstances are an exception to the preexisting duty rule.
D) Bruce will not be required to pay because he provided no additional consideration, and the preexisting duty rule applies.
E) Bruce will only be required to pay ½ of the agreed upon amounts because of the calculations involved under the preexisting duty rule.