Multiple Choice
Which of the following phases of the business continuity plan involves executing simulated scenarios of disasters and having employees execute on a disaster recovery plan?
A) Maintenance
B) Implementation
C) Testing
D) Design
Correct Answer:

Verified
Correct Answer:
Verified