Multiple Choice
Dover Enterprises recently used 14,000 labor hours to produce 7,500 completed units.According to manufacturing specifications,each unit is anticipated to take two hours to complete.The company's actual payroll cost amounted to $158,200.If the standard labor cost per hour is $11,Dover's labor rate variance is:
A) $4,200U.
B) $4,000F.
C) $4,300U.
D) $4,300F.
E) None of thesE.
Correct Answer:

Verified
Correct Answer:
Verified
Q10: When using a balanced scorecard, a company's
Q38: A favorable labor efficiency variance is created
Q58: Standard costs:<br>A)allow a manager to assess the
Q61: Taylor's direct-labor rate variance was<br>A)$6,600F.<br>B)$6,600U.<br>C)$2,960F.<br>D)$2,960U.<br>E)None of thesE.<br>
Q62: Consider the following information: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2489/.jpg" alt="Consider
Q65: A production supervisor generally has little influence
Q66: Listed below are five variances (and possible
Q68: Swedish Cruise Lines (SCL), which operates in
Q68: The direct-labor rate variance is:<br>A)$8,900F.<br>B)$8,900U.<br>C)$9,000F.<br>D)$9,000U.<br>E)None of thesE.<br>
Q74: A direct-material quantity variance can be caused