    The Critical Path in a PERT Chart Represents
Solved

The Critical Path in a PERT Chart Represents

Question 22

Question 22

Multiple Choice

The critical path in a PERT chart represents:


A) The tasks that must be completed without errors.
B) The path of processes that is critical for system adoption.
C) The most important tasks of the whole project.
D) The longest path of tasks needed for project completion.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q17: The IFAC suggested ten core principles of

Q18: The design phase of the SDLC begins

Q19: What can be done to combat scope

Q20: Which phase of the systems development life

Q21: The project sponsor generally obtains necessary resources

Q23: Control Objectives for Information and related Technology's

Q24: Brainstorm a list of reasons why 68%

Q25: The PERT and Gantt charts primarily address

Q26: Which phase of the systems development life

Q27: Parallel or concurrent tasks are tasks that

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines