Multiple Choice
Which of the following is not one of the tenets in the Agile Alliance's manifesto?
A) Satisfy the customer through early and continuous delivery of valuable software
B) Do not allow changing requirements, especially late in development
C) Business people and developers must work together daily throughout the project
D) All of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q4: Project _ are any measurable, tangible, verifiable
Q14: The rapid application development methodology emphasizes extensive
Q21: Which of the following is a characteristic
Q25: What is the critical path?<br>A) The path
Q30: _ revenues are a business-related consequence of
Q32: A prototype is a smaller-scale representation or
Q60: Project milestones are any measurable, tangible, verifiable
Q63: Project _ is a formal, approved document
Q91: What breaks a project into tiny phases,
Q93: Managing people is one of the hardest