Multiple Choice
What is the critical path?
A) The path from resource to task that passes through all critical components of a project plan
B) The path between tasks to the projects finish that passes through all critical components of a project plan
C) The path from start to finish that passes through all the tasks that are critical to completing the project in the shortest amount of time
D) The path from start to finish that passes through all the tasks that are critical to completing the project in the longest amount of time
Correct Answer:

Verified
Correct Answer:
Verified
Q21: A project _ is a formal, approved
Q24: Explain change management and how an organization
Q29: Who is the person or group who
Q30: A(n) _ is a temporary endeavor undertaken
Q52: Who are individuals and organizations actively involved
Q58: Which of the following is not a
Q63: Describe the two primary diagrams most frequently
Q68: An organization must identify what it wants
Q70: Which of the following is not a
Q128: What is a project manager?<br>A) The application