Multiple Choice
At the project level,all of the following are examples of oversight activities EXCEPT
A) Review project objectives.
B) Track and assist the project to resolve bottlenecks.
C) Project selection.
D) Review status reports.
E) Audit and review lessons learned.
Correct Answer: