Question 31

Multiple Choice

During which of the following phase gates would the questions "Were the project scope objectives met?" and "Were project cost and schedule met?" be answered?


A) Proposal.
B) Screening and selection.
C) Implementation.
D) Progress evaluation.
E) Closure.

Correct Answer: