Multiple Choice
During which of the following phase gates would the questions "Are the resources needed identified and available?" and "Are tasks sequenced and is a time-phased budget established?" be answered?
A) Proposal
B) Screening and selection
C) Implementation plan
D) Progress evaluation
E) Closure
Correct Answer: