Question 25

Multiple Choice

Which of the following is NOT one of the growth levels in the Organizational Project Management Maturity Model (OPM3TM) ?


A) Repeatable (formal application of project management) .
B) Defined (institutionalization of project management) .
C) Managed (management of project management system) .
D) Expanded (expansion of project management system) .
E) Optimized (optimization of project management system) .

Correct Answer: