Multiple Choice
Project audits are performed on all significant projects and lessons learned are recorded and used on subsequent projects in which of the following Project Management Maturity Model Levels?
A) Ad hoc project management.
B) Formal application of project management.
C) Institutionalization of project management.
D) Management of project management system.
E) Optimization of project management system.
Correct Answer:

Verified
Correct Answer:
Verified