Multiple Choice
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the
A) 0/100 percent rule.
B) Task complete rule.
C) Degree complete rule.
D) Work complete rule.
E) Percent complete rule.
Correct Answer:

Verified
Correct Answer:
Verified
Q14: The PV, AC and CV are all
Q44: Schedule variance (SV) is in dollars and
Q47: Which performance index is the most potentially
Q73: A project monitoring system involves all of
Q74: A scope change is always viewed negatively
Q76: When reviewing the variance on a project,
Q77: The second step in the project control
Q77: What is scope creep and how does
Q79: A project can have a negative Schedule
Q81: The first step in the project control