Multiple Choice
Cost slope can be determined by dividing the
A) Run by the rise.
B) Rise by the run.
C) Crash cost by the normal cost.
D) Normal cost by the crash cost.
E) Indirect cost by direct cost.
Correct Answer:

Verified
Correct Answer:
Verified