Multiple Choice
In selecting the best activity to crash you would first select the activity with the
A) Earliest start time.
B) Most steep slope.
C) Least steep slope.
D) Longest duration.
E) Largest crash time.
Correct Answer:

Verified
Correct Answer:
Verified