Multiple Choice
When it is necessary to reduce project duration and resources are constrained, which of the following is NOT a reasonable option?
A) Establishing a core project team
B) Fast-tracking
C) Reduce project scope
D) Compromise quality
E) Critical-chain project management
Correct Answer:

Verified
Correct Answer:
Verified