menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 2
  4. Exam
    Exam 9: Reducing Project Duration
  5. Question
    ____________ Is the Rearranging of the Project Network Logic So
Solved

____________ Is the Rearranging of the Project Network Logic So

Question 91

Question 91

Short Answer

____________ is the rearranging of the project network logic so that critical activities are done in parallel rather than sequentially.

Correct Answer:

verifed

Verified

Fast-tracking
Explanation: Fas...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: The easiest way to add more labor

Q20: Total cost for specific project durations is

Q36: Direct costs are so named because they

Q48: Brooks' law states that adding manpower to

Q82: Managers have several effective methods for crashing

Q87: As a project is crashed and project

Q88: Crashing a more expensive activity may be

Q89: All of the following are disadvantages of

Q94: When reducing project duration, the crash cost

Q99: What is crashing? Include a discussion of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines