Multiple Choice
Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained.
A) Time, quality
B) Quality, resource
C) Cost, time
D) Quality, cost
E) Time, resource
Correct Answer:

Verified
Correct Answer:
Verified