Multiple Choice
Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization.She should first identify activities with the
A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.
Correct Answer: