Multiple Choice
The lowest element in the hierarchical breakdown of the WBS is
A) A deliverable.
B) A work package.
C) A cost account.
D) A lowest sub-deliverable.
E) An object.
Correct Answer:

Verified
Correct Answer:
Verified