Multiple Choice
The following are responsibilities of the governance team when managing a portfolio system EXCEPT
A) Deciding how they wish to balance the available organizational resources among the different types of projects.
B) Publishing the priority of every project and ensuring the process is open and free of power politics.
C) Evaluating the progress of the projects in the portfolio.
D) Constant scanning of the external environment to determine if organizational selection criteria need to be changed.
E) Communicating which projects are approved.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: Starting and stopping work on one task
Q14: If a proposed project does not meet
Q21: The financial model that measures the time
Q32: Mission statements typically change frequently, responding to
Q48: In classifying the kinds of projects an
Q50: A proposed project that ranks high on
Q53: Intermittent scanning of the external environment is
Q58: The assessment of the external and internal
Q83: One who endorses and lends political support
Q93: Which of the following is NOT one