Multiple Choice
Bryan Inc.produces a specialty top-quality juice machine.The product,the JM50,requires four processes to be completed.Specifically,these processes are exterior construction,pulp filter insertion,painting,and packaging.Each process is performed at separate workstations with different completion rates:
Exterior construction can manufacture 100,000 juicer exteriors per day.
Pulp filter insertion can install 25,000 filters every 6 hours.
Painting can decorate 3,000 juicers every half hour.
Packaging can package 5,000 juicers per hour.
The plant operates 24/7,24 hours a day every day of the week.
Which function(s) is/are the bottleneck(s) ?
A) Exterior construction and pulp filter insertion.
B) Pulp filter insertion.
C) Painting.
D) Packaging.
E) Exterior construction.
Correct Answer:

Verified
Correct Answer:
Verified
Q23: Concurrent engineering relies on an integrated approach,
Q34: Amanda Jones owns and operates Motorcycle Rentals
Q35: Lens Care Inc.(LCI)manufactures specialized equipment for polishing
Q36: Suzy Co.produces and sells three products (X,Y,and
Q37: Generally,firms will price a product more competitively
Q40: Johnson Marine has the following costs and
Q42: Lens Care Inc.(LCI)manufactures specialized equipment for polishing
Q43: Bryan Inc.produces a specialty top-quality juice machine.The
Q71: During the sales life cycle, which is
Q82: When a firm determines the desired cost