Bryan Inc.produces a specialty top-quality juice machine.The product,the JM50,requires four processes to be completed.Specifically,these processes are exterior construction,pulp filter insertion,painting,and packaging.Each process is performed at separate workstations with different completion rates:
Exterior construction can manufacture 100,000 juicer exteriors per day.
Pulp filter insertion can install 25,000 filters every 6 hours.
Painting can decorate 3,000 juicers every half hour.
Packaging can package 5,000 juicers per hour.
The plant operates 24/7,24 hours a day every day of the week.
What is the least amount of monthly capacity you would have to add to the bottleneck(s) to shift the bottleneck to a different process?
A) 2,000,001 juicers per month.
B) 600,001 juicers per month.
C) 1,320,001 juicers per month.
D) 50,001 juicers per month.
Exterior: 100,000 x 30 = 3m
Pulp filter: 25,000 x 24/6 x 30 = 3m
Painting: 48 x 3,000 x 30 = 4,320,000
Packaging: 24 x 5,000 x 30 = 3.6m
Add 600,001 to Exterior and to Pulp Filter,would move the constraint to Packaging
Correct Answer:

Verified
Correct Answer:
Verified
Q22: Precision Instruments, Inc. is a national firm
Q47: Jamestown Furniture Co.is a small,but fast-growing manufacturer
Q48: In order to reduce costs so as
Q49: Ken Yalters,the COO of FreshSkin,asked his cost
Q51: Quality Chairs Inc.(QC)manufactures chairs for industrial use.Laura
Q53: The management accountant at Jang Manufacturing Co.collected
Q54: Excel Manufacturing has received an order for
Q60: Place the five steps in implementing a
Q64: Target cost can be defined as:<br>A) Manufacturing
Q91: Activity-based costing (ABC) and the theory of