Xero Company's standard factory overhead rate is $3.75 per direct labor hour (DLH) ,calculated at 90% capacity = 900 standard DLHs.In December,the company operated at 80% of capacity,or 800 standard DLHs.Budgeted factory overhead at 80% of capacity is $3,150,of which $1,350 is fixed overhead.For December,the actual factory overhead cost was $3,800 for 840 actual DLHs,of which $1,300 was for fixed factory overhead.Under a three-way breakdown (decomposition) of the total overhead variance,what is the total factory overhead spending variance for December?
A) N/A-this variance doesn't exist under a three-way breakdown of the total overhead variance.
B) $225 favorable.
C) $425 unfavorable.
D) $560 unfavorable.
E) $600 unfavorable.
Correct Answer:

Verified
Correct Answer:
Verified
Q50: If standard cost variances are allocated (i.e.,
Q87: The term used to refer to persistent
Q90: Gerhan Company's flexible budget for the units
Q92: Bluecap Co.uses a standard cost system and
Q93: Bluecap Co.uses a standard cost system and
Q94: Xero Company's standard factory overhead rate is
Q97: Neptune Inc.uses a standard cost system and
Q98: The following information is available from the
Q99: McAllister Company's master budget for the year
Q100: The following information is available from Thinnews