Which of the following is true of the triple constraint in projects?
A) The time constraint is the most critical of the three constraints in projects.
B) The three fundamental project constraints are insulated from each other.
C) Changes in one fundamental constraint affect the other constraints as well.
D) Cost constraints take precedence over time and scope constraints in all projects.