Multiple Choice
The term ________ refers to the way in which features are added in an uncontrolled way, often without considering the impact on the budget or timeline.
A) cone of uncertainty
B) scope creep
C) risk appetite
D) conceptual fusion
Correct Answer:

Verified
Correct Answer: