A ________ Lists Tasks on the Work Breakdown Structure, Along

Question 72

Multiple Choice

A ________ lists tasks on the work breakdown structure, along with each task's projected start and finish dates, in graphical format.


A) cluster diagram
B) Gantt chart
C) PERT network chart
D) conceptual graph