Multiple Choice
Which of the following is true about work breakdown structure?
A) It is generally created during the executing process of a project.
B) A word processor is the best software package to create work breakdown structures.
C) Work breakdown structures are used only to plan and list the tasks a team must complete.
D) Gantt charts are generally used to show work breakdown structures.