Multiple Choice
The ________ refers to the longest course through the project, which identifies those tasks that cannot be delayed without affecting the finish date.
A) graph bandwidth
B) critical path
C) long tail
D) degree sequence
Correct Answer:

Verified
Correct Answer:
Verified