Multiple Choice
Which of the following challenges is typically a feature of the closing phase of a project?
A) motivating project stakeholders
B) documenting lessons learned
C) creating a work breakdown structure
D) implementing mitigation strategies
Correct Answer:

Verified
Correct Answer: