Which of the following is a drawback of the waterfall method?
A) It is unable to adapt to changes in the business landscape.
B) Several activities occur at the same time, which makes it hard to monitor them.
C) Once a task is completed, it cannot be changed.
D) Its SDLC tasks occur in a nonsequential manner.