Multiple Choice
The ________ compresses the time horizon for software development and focuses on the time available until the next release while the development team determines how many of the requirements it can deliver in that time frame.
A) iterative method
B) waterfall method
C) agile
D) V-model
Correct Answer:

Verified
Correct Answer:
Verified