Multiple Choice
A project has the following cash flows: C0 = -100,000; C1 = 50,000; C2 = 150,000; C3 = 100,000.If the discount rate changes from 12% to 15%,what is the CHANGE in the NPV of the project (approximately) ?
A) 12,750 increase
B) 12,750 decrease
C) 14,240 increase
D) 14,240
Correct Answer:

Verified
Correct Answer:
Verified
Q15: The accounting break-even point occurs when<br>A)the total
Q18: One can employ simulation models to<br>I.understand the
Q35: Discuss the importance of conducting postaudits.
Q40: Briefly discuss break-even analysis.
Q42: All else equal, an increase in fixed
Q57: Generally,postaudits for projects are conducted to:<br>I.identify problems
Q58: The following are real options EXCEPT:<br>A)stock options.<br>B)timing
Q58: Indicate some of the problems associated with
Q61: Tangible assets usually have higher abandonment values
Q62: Firms that operate at break-even on an