Multiple Choice
Given the following cash flows for project A: C0 = -3,000,C1 = +500,C2 = +1,500,and C3 = +5,000,calculate the NPV of the project using a 15% discount rate.
A) $5,000
B) $2,352
C) $3,201
D) $1,857
Correct Answer:

Verified
Correct Answer:
Verified