Multiple Choice
In an adaptive or change - driven project life cycle:
A) the product or deliverable is well understood.
B) planning precedes all executing.
C) early results lead into planning later work.
D) the waterfall approach is commonly used.
Correct Answer:

Verified
Correct Answer:
Verified