    Portfolios Deal with All of an Organization's Projects,while Programs Deal
Solved

Portfolios Deal with All of an Organization's Projects,while Programs Deal

Question 36

Question 36

Multiple Choice

Portfolios deal with all of an organization's projects,while programs deal with:


A) ongoing operations
B) a specific group of related projects
C) resource availability
D) tradeoffs between schedule,scope and quality

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q19: All of the following represent appropriate sources

Q21: Projects tend to be the primary method

Q29: Describe the relationship between the strategic planning

Q32: The organization's leadership should establish the strategic

Q33: Strategic objectives should focus decisions regarding which

Q34: The prioritization of projects in a portfolio

Q37: Figure 2-1 Project Selection and Prioritization Matrix<br>

Q39: The internal part of strategic analysis considers

Q40: The document that describes why the project

Q41: Many writers have stated that effective objectives

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines