The milestone schedule in the project charter:


A) is a schedule that provides detailed data for when each project activity should begin.
B) is a detailed schedule that shows the planned duration for every activity in the project.
C) is a summary-level schedule that identifies significant points or events in the project.
D) is a summary-level schedule that shows how major project tasks are sequenced.