menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Contemporary Project Management Study Set 2
  4. Exam
    Exam 6: Defining Scope and Constructing Work Breakdown Structures WBS
  5. Question
    The Most Conventional Approach to Create a Work Breakdown Structure
Solved

The Most Conventional Approach to Create a Work Breakdown Structure

Question 39

Question 39

True/False

The most conventional approach to create a Work Breakdown Structure is to adopt a "top-down" approach,which can be used when the project work is familiar to the team.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q5: What are some of the benefits of

Q6: The Work Breakdown Structure (WBS)is a framework

Q9: Explain how scope is defined on agile

Q29: Which of the following statements concerning work

Q35: The approved version of a work product

Q38: Work Breakdown Structures typically include one or

Q41: Work Breakdown Structures can be displayed in

Q41: Once the project is underway,each potential change

Q42: Which of the following items best describes

Q44: On agile projects,the scope definition begins with

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines