Multiple Choice
All of these are factors that could lead to a decision to buy or outsource rather than make or perform in-house,EXCEPT:
A) flexibility in procurement
B) ability to use specialized suppliers
C) inadequate capacity
D) more control over quality and time
Correct Answer:

Verified
Correct Answer:
Verified