Multiple Choice
When considering the agile project management process, at the end of each iteration
A) Team members are released to work on other projects.
B) The Scrum master assigns daily tasks to team members.
C) Product owner determines whether or not the project is complete.
D) The Scrum master can terminate the project.
E) Stakeholders and customers review progress and reevaluate priorities.
Correct Answer:

Verified
Correct Answer:
Verified