Multiple Choice
Which of the following is NOT a wrap-up closure activity that might be found on a checklist?
A) Getting delivery acceptance from the customer
B) Reassigning project team members
C) Closing accounts and seeing all bills are paid
D) Evaluation of team performance
E) Creating a final report
Correct Answer:

Verified
Correct Answer:
Verified