Because of Circumstances Beyond the Control of the Project Team

Question 94

Multiple Choice

Because of circumstances beyond the control of the project team, many projects are easy for a review group to close down.This type of project closure is called


A) Normal.
B) Premature.
C) Perpetual.
D) Failed project.
E) Changed priority.