Multiple Choice
Which part of the final report examines in detail the underlying causes of problems, issues, and successes relative to the project and includes concise, factual review statements of the project?
A) Executive summary
B) Review and analysis
C) Recommendations
D) Lessons learned
E) Appendix
Correct Answer: