Multiple Choice
An analysis carried out during and shortly after the project life cycle that attempts to capture positive and negative learning is represented in which of the following?
A) Scenario analysis
B) Variance analyses
C) Lessons learned
D) Performance evaluation
E) Strategic objectives
Correct Answer: